Te Waireka

Te Waireka sporting new switch room

17 December 2020

The first of two new switch rooms has arrived at the Te Waireka substation. This is stage two of a three stage project that...

READ MORE

Te Waireka substation ready for new gear

26 November 2020

Work on stage two of The Lines Company’s (TLC) Te Waireka substation upgrade is near completion. This project will...

READ MORE

First 15 megawatt transformer arrives at Te Waireka, Ōtorohanga

4 May 2018

After several months’ preparation, the first of The Lines Company’s (TLC) new 15 Megawatt (MW) transformers arrived at...

READ MORE

Heavy lift the next step in Te Waireka Substation Upgrade

27 March 2018

Today six, large pre-cast concrete panels were lifted into place as the next step in The Lines Company’s (TLC) upgrade of...

READ MORE

Te Waireka substation transformer work starts

27 February 2018

Work on upgrading transformers at The Lines Company’s (TLC) Te Waireka substation at Te Waireka Road, Ōtorohanga is set to...

READ MORE